31 Mar 2008

-
Naden Mill post remediation
Site Investigation and Remediation - Former Cotton Mill & Rubber Products Factory
Following previous use as a cotton mill and subsequently a rubber products factory, BAE Systems Environmental were commissioned to undertake an updated assessment of ground, gas and groundwater conditions of the 9 acre site to support residential development.
The results of the investigation enabled the conceptual site model to be refined to identify contamination from hydrocarbon impacted soils and waste oil in a culvert associated with the old mill. Ash bearing soils were also present at or near the ground surface. Potential risks to future residents were identified as well as to a river flowing through the middle of the site.
A remediation strategy was developed and agreed with the local planning authority and the Environmental Agency with BAE Systems Environmental contracted to implement remediation of the site.
Remediation included the following activities: -
|
Following completion of remediation site works a completion report was approved by the regulators and the site was successfully developed for residential use.